Construction contracts sometimes end before the final account is settled. A contractor may send a payment claim, continue discussing outstanding costs, and later discover that the amount claimed needs to change. It might seem straightforward to withdraw the earlier claim and issue a replacement. The NSW Supreme Court’s decision in Reosteel Pty Ltd v Reem Built Pty Ltd [2026] NSWSC 1348 demonstrates why that assumption can be costly. Pike J held that, under the NSW security of payment legislation, a claimant that has served its payment claim after termination cannot unilaterally withdraw it and serve another. An adjudication determination awarding A$132,850.34, together with interest and adjudication fees, was quashed. For contractors and advisers, the decision highlights the importance of preparing a payment claim after termination with a clear understanding of the statutory consequences. For adjudicators, it reinforces the need to establish whether the claim can validly engage the statutory process before assessing the amount payable. The background
Reem Built Pty Ltd performed work on several projects associated with a common director. Two were relevant: residential alterations and repairs at Monterey, and refurbishment work at commercial premises in Casula. The Monterey work was invoiced to BBLC Building Supplies Pty Ltd, while the Casula work was invoiced to Reosteel Pty Ltd. On 29 July 2025, the parties mutually agreed that Reem would perform no further construction work for entities associated with the director. On 16 August 2025, Reem sent correspondence setting out the final amounts outstanding. This included a tax invoice to Reosteel for the Casula project claiming A$45,290.15 including GST. The invoice expressly identified itself as a payment claim under the Building and Construction Industry Security of Payment Act 1999 (NSW), referred to here as SOPA. Reosteel did not respond to that claim. On 15 June 2026, Reem served a further final payment claim for A$132,850.34 including GST. The accompanying material withdrew previous discounts, concessions and alternative payment arrangements, and sought the full value of the work and associated charges. Reosteel responded with a payment schedule proposing to pay nothing. Reem applied for adjudication and, on 24 July 2026, obtained a determination for the full amount claimed, interest and all adjudication fees. Reosteel then challenged the determination in the Supreme Court. [Judgment, paragraphs 6–31.] The central issue By the hearing, Reem was no longer pursuing its argument that the August 2025 invoice was not a statutory payment claim. The Court therefore proceeded on the basis that an earlier payment claim had already been served after termination. The question was whether Reem could withdraw that claim and replace it with the June 2026 claim. Section 13(1C) of SOPA permits a payment claim to be served from the date a construction contract is terminated. Although the provision does not expressly use the words “only one”, earlier authority had construed it as allowing only one payment claim after termination. Reem argued that withdrawal and replacement remained possible. [Judgment, paragraphs 34–39.] Why the replacement claim failed Pike J followed BCFK Holdings Pty Ltd v Rork Projects Pty Ltd [2022] NSWSC 1706. That decision considered the wording, statutory context and legislative history of section 13(1C), and concluded that only one payment claim may be served after termination. Reem relied on authorities discussing the withdrawal and replacement of payment claims, including NC Refractories, Kitchen Xchange and Taylor Construction. The Court examined those authorities carefully. Some predated section 13(1C), and the authorities were generally understood as supporting withdrawal by agreement. There was no suggestion that Reosteel had agreed to withdraw the first claim. Pike J considered that allowing a claimant to withdraw and replace a claim unilaterally would substantially undermine the statutory limit. A claimant could otherwise exercise its entitlement after termination, reverse that step, and exercise it again. Reem argued that the restriction could produce an unreasonable result where a contractor received a further invoice after serving its claim. The Court rejected that argument: the contractor could wait until it had received the invoices it wished to include. In practice, that approach must still be managed within the applicable statutory and contractual time limits. Reem also relied on Reosteel’s failure to respond to the first claim. That did not change the statutory construction. The claimant’s ability to serve another claim did not depend on the respondent’s subsequent conduct. The Court held that the entitlement had already been exercised. Describing the later claim as a replacement could not avoid the limitation. [Judgment, paragraphs 43–59.] Withdrawing a concession is different from withdrawing a claim The Court also addressed the wording of the June 2026 claim, although this was unnecessary to its decisive conclusion. The claim expressly withdrew earlier discounts and concessions. It did not expressly withdraw the earlier payment claim. Pike J distinguished the two: changing the amount sought concerns the substance of the demand, while withdrawing a payment claim concerns the status of the earlier statutory document. His Honour accepted that a skilled reader considering all the material would probably understand the later claim as intended to replace the first, but the position could have been clearer. Even a clearer statement of unilateral withdrawal would not have overcome the statutory obstacle identified by the Court. [Judgment, paragraphs 60–64.] The separate licensing and insurance argument Reosteel also argued that Reem was disentitled to progress payments because its contractor’s licence was restricted to contracts not requiring Home Building Compensation Fund insurance. The argument depended on treating the residential Monterey work and the commercial Casula work as part of one overarching construction contract. Reosteel contended that the residential work affected Reem’s entitlement to payment under that wider arrangement through section 8(2) of SOPA. The Court rejected the factual premise. A December 2024 text message proposing rates for future work was better understood as a standing offer capable of acceptance when particular work was requested. The separate project instructions and invoicing supported separate contracts. A common director’s involvement across associated companies did not establish that those companies were parties to one construction contract. Pike J therefore rejected this ground of challenge. His Honour also considered Reem’s alternative reliance on section 98 of the Home Building Act 1989 (NSW), concerning insurance obligations where work is performed for another person required to insure it, but found the necessary factual basis had not been established. That discussion should not be read as a general exemption from contractor licensing requirements. [Judgment, paragraphs 65–89.] The outcome and its limits The successful challenge to the second payment claim was sufficient to dispose of the proceedings. The Court quashed the adjudication determination, ordered Reem to pay Reosteel’s costs, and directed that the money Reosteel had paid into Court be returned with accrued interest. [Judgment, paragraphs 90–92.] The decision concerns the availability of the statutory payment and adjudication process for the later claim. It did not determine the final contractual balance between the parties. Quashing the determination should therefore not be equated with a finding that Reem had performed no compensable work or that no underlying debt existed. The distinction between unilateral withdrawal and withdrawal by agreement also matters. The Court recognised authorities concerning agreed withdrawal, but there was no agreement here. The decision should not be presented as determining the validity of every replacement claim made in different circumstances. Practical lessons For claimants, the first step is to audit the correspondence already sent after termination. A document labelled as a tax invoice may also be a statutory payment claim, as happened here. Preparing a later document called a final claim does not necessarily create a fresh entitlement to invoke SOPA. Before serving a claim after termination, reconcile the account, check outstanding supplier and subcontractor invoices, identify the correct contracting party, and review the applicable deadlines. Commercial urgency needs to be balanced against the consequences of using the statutory entitlement before the account is ready. For respondents, the payment claim history can be as important as the valuation. Check whether an earlier claim was served after termination and whether any withdrawal was actually agreed. A suspected defect should be addressed promptly through the applicable response process. For adjudicators, the case illustrates why statutory entitlement and contract identification require careful attention. The amount claimed may be supported by substantial records, but those records do not answer whether the particular claim can engage the legislation. Equally, related projects and associated companies require examination of the actual contractual arrangements. Relevance for New Zealand readers Reosteel interprets specific NSW statutory provisions. It does not establish a corresponding one-claim rule under New Zealand’s Construction Contracts Act 2002. Any New Zealand question must be assessed under that Act, the relevant contract and the facts. For me, the broader lesson is the importance of reviewing the entire payment history before choosing the next procedural step. Termination, earlier claims, settlement proposals and the identity of the contracting parties can all affect the analysis. A revised amount or a new label on a document cannot be assumed to reset the statutory process. Source: Reosteel Pty Ltd v Reem Built Pty Ltd [2026] NSWSC 1348, judgment delivered 30 October 2026, including the typographical amendment recorded that day. Paragraph references above refer to this judgment. Disclaimer: This article is for general information only and does not constitute legal advice. Each matter turns on its own facts, contract terms, and evidence.
0 Comments
Your comment will be posted after it is approved.
Leave a Reply. |
AuthorJoem is a Dispute Resolution Practitioner, Construction Law specialist and a practicing Quantity Surveyor with a strong background in Civil Engineering and Project Management. Archives
October 2026
Categories
All
|
RSS Feed